Welcome to the 25 River Boulevard Construction Update Landing Page
Stay informed with the latest updates on the construction of 25 River Boulevard. This page is your go-to resource for key construction milestones, timelines, and what to expect as works progress. Whether you're a resident, neighbour, or local business, we’re committed to keeping you informed every step of the way.
For any construction questions or concerns email the team at mail@lusimon.com.au.
If you have any questions about the project, please fill out the form below or email us at 25riverboulevard@salta.com.au.
July 2025 Works Update
We are progressing on the construction of 476 new homes for Salta Properties at 25 River Boulevard, Richmond. Site retention works are commencing to enable the excavation of the basement.
What is happening?
- Asbestos remediation works will conclude over the next month
- Hoardings will be erected around the site perimeter over the next few weeks
- Site retention works are commencing
- Piling works have commenced.
- Steel reinforced concrete capping beams will be constructed along the top of the piles.
- Bulk excavation of the site will commence
What will you see and hear?
- Increased activity on site, including trucks and machinery.
- As these works progress you will start to see the outline of the basement taking shape.
- Some dust and machinery noise.
- Plant will operate in accordance with safety and noise regulations for commercial construction activities.
- Traffic management will be in place. Please observe all safety signage.
- We will do our best to minimise any inconvenience.
Construction Timeline
- Piling -July 2025- March 2026
- Structural Completion -Early 2027
- Overall Construction Completion - Late 2027
Working hours
- Monday- Friday 7.00 am - 6.00 pm
- Saturday 7.00 am - 3.00 pm
Safety on site
- Dust suppression practices and noise reduction equipment implemented to reduce impacts as much as possible.
- All works will be inside the fenced construction site and closely monitored.
- All works will be compliant with WorkSafe Victoria, City of Yarra Local Laws and Environmental Protection Authority (EPA) Victoria regulations.
- We appreciate your patience while we undertake these important works.
We appreciate your patience while we undertake these important works.